Canada Invests $29M in Calgary Water
Project to deliver 100 million litres of drinking water to north Calgary by 2029, with 30 million litres added next year

The federal government has committed $29 million to the North Calgary Water Servicing project, a major infrastructure initiative aimed at delivering 100 million litres of drinking water to north Calgary communities. The project has a total budget of $533 million and is expected to be fully built out by 2029.
The first phase of the project is set to cost $123 million, with the city contributing $94 million. This initial stage includes the construction of several kilometres of feeder main, as well as upgrades to connect existing facilities such as the Top Hill Reservoir, Big Hill East Reservoir, and Mountain View Pump Station.
The federal funding, provided through the Build Communities Strong Fund, will support the first stage of the project, which is expected to provide 30 million additional litres of water to Calgarians from the Bearspaw Water Treatment Plant next year. The north feeder main will ultimately run 22 kilometres and include up to 10 support facilities when complete.
## What the project means for Calgarians The North Calgary Water Servicing project is a significant investment in the city's infrastructure, aimed at ensuring a reliable supply of drinking water for its residents. The project's completion is expected to have a positive impact on the daily lives of Calgarians, providing them with access to clean and safe drinking water.
The federal government's commitment to the project demonstrates its recognition of the importance of investing in Canada's infrastructure. The project is expected to support the city's growing population and economy, while also ensuring that residents have access to essential services like clean drinking water.
## Next steps The project is currently underway, with the first phase expected to be completed next year. The remaining phases will be completed over the next several years, with the project expected to be fully built out by 2029. The city and federal government will continue to work together to ensure the project's successful completion and that it meets the needs of Calgarians.